Construction for a retaining wall located between the Moraga Drive on-ramp and off-ramp will occur from July 15 to July 26.
Activities consist of excavation and demolition of pre-existing wall, and haul-out of debris. Work hours are from 9 p.m. to 6 a.m.
Excavation will occur from Monday, July 15 to Saturday, July 20.
Demolition of pre-existing retaining wall will occur from Monday, July 22 to Wednesday, July 24.
Find out what's happening in Brentwoodfor free with the latest updates from Patch.
Haul out of demolition debris will occur from Thursday, July 25 to Friday, July 26.
This work will require closure of the Moraga Drive on-ramp and off-ramp.
Find out what's happening in Brentwoodfor free with the latest updates from Patch.
This work will utilize the full Sepulveda Boulevard closure from Montana Avenue to Moraga Drive which has been implemented regularly for three months, from 11 p.m. to 6 a.m.