Pile driving, which is an essential step in the construction of the foundation of the grade separation, began in February. Pre-drilling holes in preparation for the resumption of pile driving will begin on June 4. The pile driving will be limited to weekday daytime hours from 9 a.m. to 3 p.m. The work will involve excavation and drilling into the ground.
Other work, which includes digging with a backhoe and mini-excavator will be done from 7 a.m. to 4 p.m. Crews will excavate, install temporary shoring, install culverts, install utility infrastructure, prepare foundations, install rebar and pour concrete. Crews will use medium and heavy duty diesel vehicles to transport dirt and concrete.
Night work will occur from Sunday, June 3, through Friday, June 8, between 11 p.m. and 7 a.m. Crews will install utilities, excavate, and install temporary shoring in preparation for pouring foundations and building retaining walls.
Find out what's happening in San Brunofor free with the latest updates from Patch.
The $147 million project will elevate the Caltrain tracks above three existing at-grade street crossings at San Bruno, San Mateo and Angus avenues. A new elevated Caltrain station between San Bruno and San Mateo avenues will replace the station at Sylvan Avenue.
For more information, please call the dedicated outreach line at 650-508-7726 or email sbgradesep@caltrain.com.