CT Water Resumes Construction in Mansfield

Connecticut Water will resume water main installation work on Route 195 in Tolland and Mansfield this week.

The Connecticut Water Company sent in the following update:

Beginning the week of March 7, Connecticut Water will resume water main installation work on Route 195 in Tolland and Mansfield. A crew will be working in Tolland just east of Anthony Road where the road is narrower so there may be some impact to traffic in this area. A second crew will be working in the vicinity of Baxter Road in Mansfield where the road is wider and we expect to maintain two lanes of traffic for the majority of the time.

Work hours are 6:30 a.m. to 2:30 p.m. Monday through Friday.
54653cec-c1d7-4cf0-8e75-4e1737694d32.png

Pipeline installation has been completed on Route 195 between the Four Corners and Mansfield Supply, and on Route 44 between the Four Corners and Jensen’s Rolling Hills Community.

Overall the project is about 62% complete with more than 3.5 miles of water main installed since mid-July.

Updates on the pipeline construction and traffic related information are available via e-mail and text directly from Connecticut Water by signing up here.

Current Traffic

Find out what's happening in Mansfield-Storrsfor free with the latest updates from Patch.

Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.