It's that season again. With warmer weather comes road construction, especially in north Nichols.

Construction work is anticipated to start at 7 a.m. daily. Here's a four-week look-ahead:

  • Week of June 10th, 2013:
Drainage construction will occur on the following roads: Saybrook Road, Partridge Lane, Hilltop Circle, Rennison Road, Old Green, Hillandale Terrace, Irwin Street
Roadway Excavation will begin on: Columbine Road, Tamarack Circle, Heartwood Lane, Kenwood Lane, Ethel Road, Oriole Circle, Rennison Road. 

  • Week of June 17th, 2013:
Drainage construction will occur on the following roads: Saybrook Road, Partridge Lane, Old Green Road, Hillandale Terrace, Skyview Drive, Pachaug Road, Irwin Street
Roadway Excavation/Paving will continue on: Columbine Road, Tamarack Circle, Heartwood Lane, Kenwood Lane, Ethel Road, Oriole Circle, Rennison Road, Old Green Road. 

  • Week of June 24th, 2013:
Drainage construction will occur on the following roads: Hillandale Terrace, Skyview Drive, Pachaug Road, Irwin Street
Roadway Excavation/Repaving will continue on: Columbine Road, Tamarack Circle, Heartwood Lane, Kenwood Lane, Ethel Road, Oriole Circle, Rennison Road, Old Green Road. 

  • Week of July 1st, 2013:
Drainage construction will occur on the following roads: Skyview Drive, 
Roadway Excavation/Repaving will continue on: Columbine Road, Tamarack Circle, Heartwood Lane, Kenwood Lane, Ethel Road, Oriole Circle, Rennison Road, Old Green Road.