State Awards Contract for GA 400 Toll Demolition
Tolls end in November with major demolition work beginning in January.

The State Road & Tollway Authority (SRTA) has awarded a Newnan company theΒ GA 400 toll booth demolition contract.
Low bidderΒ Southeastern Site Development Inc., which specializes in transportation, civil, site preparation, underground utilities and concrete flatwork projects, will complete the nearly year-long project for $3.5 million.Β
βI acted as quickly as the stateβs contractual obligations allowed to bring down the GA 400 toll,β said Gov. Nathan Deal, who serves as chair of the SRTAΒ board, in a press release. βI pledged during my campaign for governor that Iβd bring down the toll as the state promised commuters it would do when it opened the toll more than two decades ago. Todayβs announcement is a big step toward making that happen.β
Find out what's happening in Cummingfor free with the latest updates from Patch.
In July 2012, Gov. Deal announced that the state would pay off its bond debt and end the tollsΒ by December 2013. The ending date for toll collection has been tentatively set forΒ Nov. 21. SRTA is funding the project, while the Georgia Department of Transportation will oversee construction and traffic. Β
Preliminary plans call for traffic to shift into three lanes where motorists currently use the electronic tolling lanes. Once traffic is shifted, toll booth demolition is expected to be completed between January and the following May. Once the booths and overhead structure are removed, traffic will shift over so that the rest of the toll plaza can be taken down. Once that happens, traffic will shift back over permanently.Β
Find out what's happening in Cummingfor free with the latest updates from Patch.
For drawings and more details, visitΒ www.georgiatolls.com/ga400tollboothdemolition.