The Hard Labor Creek Reservoir Management Board will meet at the Government Buildings in Monroe at 1:00 p.m. on Tuesday, April 16, 2013
Agenda
1.        Review/Approval of March 19, 2013 Meeting Minutes
Find out what's happening in Monroefor free with the latest updates from Patch.
2.        Project Financing/Budget:
- Review Monthly Construction Budget Report for March 2013
- Review Draft FY 2014 Construction Budget
3.        Land Acquisition:
Find out what's happening in Monroefor free with the latest updates from Patch.
- Monthly Progress Update:
4.        Dam/Reservoir Construction:
- Bid schedule based on completion of land acquisition (Spring-Summer 2013)
- Georgia Transmission (GTC) Relocation: Projected completion Spring 2014
5.        Road Relocations:
- Social Circle-Fairplay Road Relocation (E.R. Snell Contractor, Inc):
- Mount Paron Church Road Culvert:
6.        Raw Water Intake Facility:
- Notice to Proceed: April 8, 2013
- Construction: May 2013 – August 2014
7.        Other Business:
- Review Project Website Activity Report (hardlaborcreek.com)
- Consider Renewal of Contract and Annual Web Hosting Fee with Brown Web Design
8.        Public Comment:
9.        Executive Session to Discuss Land Acquisition Matters
10. Adjourn
Next RMB Meeting Date:Â Â Â Â Â Â Â Â May 21, 2013