High School Project on Target

Construction is also under budget, School Committee is told.

The project is 45 percent complete and remains on track for a September 2012 opening, the Grafton School Committee was told last night.

The project is also “significantly under budget,’’ Rich McCarthy, chairman of the School Building Committee, said.

The biggest challenge now is getting the windows secured for the winter, he said, to avoid increased heating costs.

Find out what's happening in Graftonfor free with the latest updates from Patch.

He also said that neighbors on Brigham Hill Road have been plagued by excess water, in large part because of the storms in August and September.

Those issues have been corrected, he said.

Find out what's happening in Graftonfor free with the latest updates from Patch.

Principal James Pignataro has visited the model classroom several times to make decision on fixtures and other features, McCarthy said.

Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.