Drivers should expect to navigate through lane closures and temporary delays as construction crews continue installing underground drainage pipes, curb and gutter, and preparing and placing asphalt for the Johnnie Dodds Boulevard Improvements Project in Mount Pleasant. All construction areas will be marked with construction cones and signs. In order to reduce impact to travelers over the Fourth of July holiday, there will be no lane closures from 6 a.m. on July 3 to 6 a.m. on July 8.
The following previously announced work will continue through Sunday, July 22:
Johnnie Dodds Boulevard Nighttime Lane Closures:
Find out what's happening in Mount Pleasantfor free with the latest updates from Patch.
- Drivers should expect temporary, nighttime lane closures for three miles on Johnnie Dodds Boulevard (U.S. Highway 17) from the end of the Arthur Ravenel, Jr. Bridge to I-526.
- The construction activity will occur from 9 p.m. - 6 a.m. in an effort to reduce the impact on drivers.
- The speed limit on Johnnie Dodds Boulevard is reduced from 45 mph to 35 mph in the construction zone.
East Frontage Road
Daytime Lane Closures:
o   Drivers should expect temporary, daytime lane closures on East Frontage Road from McGrath Darby Boulevard to Bowman Road.
o   For areas with low traffic volumes, the construction activity could occur as early as 6 a.m. until 4 p.m. Lane closures in areas of high traffic will be delayed until 8:30 a.m.
o   Drivers will have access to businesses along East Frontage Road at all times during construction.           Â
Find out what's happening in Mount Pleasantfor free with the latest updates from Patch.
Nighttime Road Closures:
o   Drivers should expect minor, nighttime road closures from 8 p.m. - 6 a.m. due to eastbound and westbound road closures of East Frontage Road from McGrath Darby Boulevard to Bowman Road.
o   The daily starting time of this closure may be delayed until 9 p.m. if traffic is heavy.
West Frontage Road
Daytime Lane Closures:
o   Drivers should expect temporary, daytime lane closures on West Frontage Road from Mathis Ferry Road to Bowman Road.
o   For areas with low traffic volumes, the construction activity could occur as early as 6 a.m. until 4 p.m. Lane closures in areas of high traffic will be delayed until 8:30 a.m.
o   Drivers will have access to businesses along West Frontage Road at all times during construction.
Nighttime Road Closures:
o   Drivers should expect minor, nighttime road closures from 8 p.m. - 6 a.m. due to eastbound and westbound road closures of West Frontage Road from Mathis Ferry Road to Bowman Road.
o   The daily starting time of this closure may be delayed until 9 p.m. if traffic is heavy.
Bowman Road Closure Over Shem Creek:
As previously announced, the current phase of the project includes the temporary closure of the portion of Bowman Road that goes over Shem Creek (between McDonald’s and Kmart on Bowman Road) while crews replace the small bridge. This closure to Bowman Road began on Monday, April 16, and will be in place for five months. Construction areas will continue to be marked with traffic control devices and signs as they are now.
Drivers will be detoured as follows:
- Those traveling east on Bowman (going from Johnnie Dodds Boulevard toward Chuck Dawley Boulevard) should use this detour:Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â http://www.ccroadwise.org/projects/johnnie_dodds/docs/1.pdf
- Those traveling west on Bowman Road (from Kmart toward Johnnie Dodds Boulevard) should use this detour:Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â http://www.ccroadwise.org/projects/johnnie_dodds/docs/4.pdf
- Those traveling south on Johnnie Dodds Boulevard heading east on Bowman Road should use this detour: http://www.ccroadwise.org/projects/johnnie_dodds/docs/2.pdf
- Those traveling north on Johnnie Dodds Boulevard heading east on Bowman Road should use this detour: http://www.ccroadwise.org/projects/johnnie_dodds/docs/3.pdf
Nighttime Entrance and Exit Ramps will continue to be closed as previously announced:
The following ramps will continued to be closed nightly from 9 p.m. – 6 a.m. (Note: only one ramp will be closed at any given time):
o   Entrance ramp onto southbound Johnnie Dodds Boulevard from Bowman Road (next to Arby’s restaurant).
o   Entrance ramp onto northbound Johnnie Dodds Boulevard from Bowman Road (next to McDonald’s restaurant).
o   Exit ramp from southbound Johnnie Dodds Boulevard onto Bowman Road (next to the former East Cooper hospital).
o   Exit ramp from northbound Johnnie Dodds Boulevard onto Bowman Road (next to Blockbuster and Nason Medical Center).
- During the nightly ramp closures, all traffic will be detoured to either East Frontage Road or West Frontage Road.
- All construction areas and detours will be marked with construction cones and signs.
In order to reduce impact to travelers over the Fourth of July holiday, ramp closures will not occur from 6 a.m. on June 30 to 6 a.m. on July 8.