Here are some highlights of projects completed by Belmont Public Works crews in 2013.
From traffic signal repairs to sewer line cleaning, Belmont's Public Works crews covered the city from end-to-end in 2013. Here's what PW crews accomplished in from January to December, according to Afshin Oskoui, the city's Director of Public Works.
Field Operations
4,347 curb miles of street sweeping
318,238 feet of Sewer line cleaning (jetting)
180,818 feet of Sewer Line videoing
7,242 feet of Storm Line videoing
334 Service Calls for sewer laterals
40,000 feet of Sanitary Sewer Root foaming
144 Street light repairs
23 Traffic Signal repairs
Graffiti removal- 43 locations
59 Potholes filled Fulfilled
355 Vehicle Repairs Requests Fulfilled
209 Vehicle Maintenance Requests
Engineering
Submitted 9 grant applications
Secured over $1.1 million funding
Adopted Complete Streets Policy
Adopted Sewer Lateral Policy
Completed 2014 Rubber Chip/SlurrySeal Project
Issued 17 Sewer Lateral Certificates
Completed Citywide Sewer Rehabilitation Project
Completed Belmont Creek Dredging Project
Completed Alameda de Las Pulgas Sewer Main Reconstruction Project
Initiated Ralston Corridor Study
Filed the Annual Water Quality Municipal Regional Permit Report Stream Stewardship
Outreach to 121 property owners along Belmont Creek
Conducted Community Outreach and Education
2 trash clean up events
8 Outreach events
Development Review and Permits:
108 Engineering plan reviews completed
163 Temp. Encroachment Permits issued
2 Transportation/Oversize Load Permits
2 Permanent Encroachment issued
6 Administrative Encroachment Permits
6 Grading Permits issued
37 Ralston Banner Permits issued
525 Permit Inspections 104 Code Enforcement Inspections
20 NPDES Business Inspections