Town Of Weston: Road Paving Update

The following is an update on the Weston Road Paving Program.

09/20/2024 9:00 AM

The following is an update on the Weston Road Paving Program. This schedule is subject to change based on weather or unforeseen circumstances. The installation of select curbing and driveway apron repairs will start where paving is completed.

Find out what's happening in Weston-Redding-Eastonfor free with the latest updates from Patch.


Paving has been completed on the following roads:
● Spruce Hill Road
● Samuelson Road
● Whippoorwill Lane
● Grey Fox Lane
● Old Farm Road
● Osborne Farm Road
● Birch Hill Extension
● Old Hyde Road Extension
● Kramer Lane

Daily work schedule (subject to change):
● Friday (9/27)
○ Paving Bottom Coat Valley Forge
● Monday (9/30)
○ Paving on Birch Hill Road
○ Paving on Davis Hill Road (subject to detour (bridge closed))
○ Milling on River Road (one way section, subject to detour)
● Tuesday (10/1)
○ Paving on Davis Hill Road (subject to detour (bridge closed))
○ Paving on Weddington Lane
○ Milling on Good Hill Road (expect traffic delays, road will remain open)
● Wednesday (10/2)
○ Paving on Valley Forge (subject to detour)
○ Milling on Good Hill Road (expect traffic delays, road will remain open)
● Thursday (10/3)
○ Paving on Valley Forge (subject to detour)

Find out what's happening in Weston-Redding-Eastonfor free with the latest updates from Patch.


This press release was produced by the Town of Weston. The views expressed here are the author’s own.