Travelers are advised delays may result from road paving work. Here's the complete schedule.

AVONDALE ESTATES, GA — Paving work began Monday in the City of Avondale Estates, according to a city statement.
Avondale Estates hired HEH Paving to pave four roads throughout the city.
The following roads will be paved during the project: North Clarendon Avenue from North Avondale Road to Old Rockbridge Road; Berkeley Road from Clarendon Avenue to Dunwick Drive; Lakeshore Drive from Hess Drive to the dead-end of Lakeshore Drive; and Hess Drive from Wiltshire Drive to the cul-de-sac.
Find out what's happening in Decatur-Avondale Estatesfor free with the latest updates from Patch.
Weather permitting, the project should be completed by November 24.
Travelers are advised delays may result.
Find out what's happening in Decatur-Avondale Estatesfor free with the latest updates from Patch.
The schedule for paving:
- Avondale Estates - N Berkeley Road - Replace 100' of Granite Curb 10/24/2016, 1 day
- Avondale Estates - N Berkeley Road - Remove and Replace 556 sf of Sidewalk/Driveway 10/24/2016, 2 days
- Avondale Estates - Lakeshore Drive (Patching 117 TN's, Edge Mill 1020 sy, 9.5 MM 126 TN's) 10/25/2016, 2 days
- Avondale Estates - Hess Drive (Patching 470 TN's, Edge Mill 4,000 sy, 9.5 MM 558 TN's) 10/27/2016, 4 days
- Avondale Estates - N Berkeley Road - (Patching 117 TN's, Edge Mill 1,528 sy, 9.5 MM 236 TN's) 11/2/2016, 2 days
- Avondale Estates - N Clarendon Ave (Patching , Full Wdth Milling 4,976sy, 12.5 MM 377 TN) 11/4/2016, 4 days
- Avondale Estates - Hess Drive Replace 75 lf of Roll Curb 11/9/2016, 1 day
- Avondale Estates - Manhole Adjustments 11/9/2016, 5 days
- Avondale Estates - Striping 11/23/2016, 2 days