Traffic Alert: Beverly Rantoul Street/1A Project Schedule
Here's what to expect the week of April 24 on Rantoul Street.

BEVERLY, MA – The Rantoul Street/1A project continues into this phase on Monday, April 24. Watch out for delays and detours in these places:
Week of April 24 - April 28:
- Monday: Test pit on water main at Gloucester Crossing.
- Monday-Friday: Install light foundations and conduit at Elliott Street.
- Monday-Friday: Plant trees Phase 1, 2 and 3.
- Monday-Friday: Install loam at Odell Park.
- Monday-Friday: Repair sprinklers and plant sod at Odell Park.
- Monday-Friday: Roadway excavation in Phase 5 section.
- Monday-Wednesday: Install signal and light conduit crossings in Phase 5 section.
Week of May 1 - May 5:
Find out what's happening in Beverlyfor free with the latest updates from Patch.
- Monday: Install light foundations and conduit at Elliott Street.
- Monday-Wednesday: Reset curb on Elliott Street.
- Tuesday-Friday: Grade sidewalks and driveways on Elliott Street.
- Monday-Friday: Repair sprinklers and plant sod at Odell Park.
- Monday-Friday: Roadway excavation in Phase 5 section.