Paving Work Coming To Natick's North Main Street: What To Know

Paving work will impact traffic on the road starting this week, officials said. Work is expected to last 10 days.

The area between Rutledge Road and Gordon Street will not be paved until school has ended for the summer on June 14.
The area between Rutledge Road and Gordon Street will not be paved until school has ended for the summer on June 14. (Neal McNamara/Patch)

News release from Town of Natick.

NATICK, MA — Paving operations are expected to cover approximately 1,000 feet per day and will pave both north and south bound lanes. One single lane of traffic will be open through the work area. The paving will proceed north-to-south, work will start at the Wayland town line and progress southerly. The paving operation is expected to last for 10 days (weeks of June 3 - 7 and June 10 -14), work will largely occur during the 7:00AM to 4:00PM hours.

TRAFFIC WILL BE IMPACTED THROUGH THE WORK AREA. AVOIDING DRIVING THROUGH THE WORK AREA WILL LESSEN DELAYS.

Find out what's happening in Natickfor free with the latest updates from Patch.

The area between Rutledge Road and Gordon Street will not be paved until school has ended for the summer on June 14th.

Pavement lane striping will be placed after the pavement surface has cured which is at least 72 hours.