What's Happening With Natick South Main Street Reconstruction Project?

The town provided an update to what's happening this week, next week and longer down the road.

The contractor has scheduled seven work days this week for the sidewalks and driveway aprons. Work may proceed faster or slower depending on the weather, officials said.
The contractor has scheduled seven work days this week for the sidewalks and driveway aprons. Work may proceed faster or slower depending on the weather, officials said. (Neal McNamara/Patch)

News release from Town of Natick.

Week of 9/25 – 9/29

Rain is predicted for Monday 9/25. The contractor will begin driveway work on the east side of road beginning Tuesday, Sept. 26th. The work will begin at Patriot Landscaping and proceed north along the east side of the road. The work will then proceed from Cottage Street south along the west side of the road. The contractor has scheduled seven work days for the sidewalks and driveway aprons. Work may proceed faster or slower depending on weather.

Find out what's happening in Natickfor free with the latest updates from Patch.

Week of 10/2 – 10/6

Sidewalk and driveway work is anticipated to be completed no later than Friday Oct 6th.

Find out what's happening in Natickfor free with the latest updates from Patch.

Longer Look Ahead

Following completion of sidewalk and driveway work, the contractor will place loam and seed along disturbed areas along the back edge of sidewalk and at access ramps. This work will include removal of weeds in front yards along the sidewalk. Sprinkler repair will occur during this work. Final punch list items will be addressed and clean will be completed. Work on South Main Street is expected to be completed by October 27th.