Wright County Government: Timeline For Co. Rd. 118 Project In Monticello Released

Subgrade Preparation – (12 workdays) Thursday July 15 through Friday July 30

July 15, 2021

The Wright County Highway Department has released a tentative time schedule for the County Road 118 (Fenning Avenue) roundabout project. All the dates and time duration for the different portions of the project are weather-dependent.

Find out what's happening in St. Michaelfor free with the latest updates from Patch.

Subgrade Preparation – (12 workdays) Thursday July 15 through Friday July 30

Place Select Granular – (9 days) Monday, July 19 through Thursday July 29

Find out what's happening in St. Michaelfor free with the latest updates from Patch.

Storm Sewer in Front of Wall – (2 days) Thursday, July 15 through Friday, July 16

Finish Grading/Base Temporary Bypass – (2 days) Friday, June 16 though Monday, June 19

Pave Temporary Bypass – (4 days) Tuesday, July 27 through Friday, July 30

Close Roundabout/Place Traffic on Bypass – (1 day) Monday, Aug. 2

Removals in Roundabout – (2 days) Monday Aug. 2 through Tuesday, Aug. 3

Underground in Roundabout – (11 days) Tuesday, Aug. 3 through Tuesday, Aug. 17

Grade Roundabout – (5 days) Tuesday, Aug. 17 to Monday, (Aug. 23)

Construction on the project is being done by Duininck, Inc. of Monticello.