East Brunswick Rejects Ice Arena Food Vendor Proposals, Approves Construction Changes
The town plans to issue a new RFP with clearer specifications and will hold a pre-submission meeting with potential vendors.

EAST BRUNSWICK, NJ – The search for a food and beverage vendor at the town's upcoming ice arena will restart after Municipal officials rejected all three proposals received through the initial bidding process.
The proposals were rejected during Monday’s meeting.
Resolution 25-290, approved at this week's council meeting, authorizes the town to reject all submissions received in connection with the Request for Proposals (RFP) for ice arena concession operations.
Find out what's happening in East Brunswickfor free with the latest updates from Patch.
According to the Director of Recreation's recommendation, two of the three submissions failed to comply with RFP requirements, while the third compliant proposal received an unfavorable review.
"We want to make sure we cross our T's and dot our I's and make sure we get it right, since this is our new ice rink," attorney Anthony Iacocca said.
Find out what's happening in East Brunswickfor free with the latest updates from Patch.
The town plans to issue a new RFP with clearer specifications and will hold a pre-submission meeting with potential vendors to better align proposals with township objectives for the food and beverage operations.
Separately, council members approved Resolution 25-296, a change order for ongoing ice arena construction that will convert an existing opening into functional loading doors.
Currently, construction crews are using a break in the cinder block wall on the building's second floor to move equipment in and out. Rather than simply closing off this opening as originally planned, officials recognized an opportunity to improve the facility's long-term functionality.
The approved modification will convert the temporary opening into proper doors that can open and close, making it significantly easier to transport heavy equipment to the second-floor storage area using lifts. Without this modification, moving equipment would require carrying items upstairs or transporting them to the opposite side of the building to use an elevator.
The second-floor storage space is intended to house equipment including artificial turf that will cover one of the ice rinks during non-hockey seasons, providing the facility with greater versatility for community events and activities.
The change order covers both the design costs and construction expenses associated with creating the permanent loading access point.