Schools
School Construction Projects βOn Targetβ For September
School officials say eight out of a total 16 voter-approved "referendum projects" are slated for completion this summer. But the overall work will still take three summers finish.
If youβre driving around Fort Lee over the next couple of months and happen to pass one of the boroughβs public schools, itβs likely youβll see a lot of activity you wouldnβt normally see during the summer.
Thatβs because construction and repair work in January, when the Fort Lee Board of Education held its third referendum since September 2010βa scaled-back, roughly $30 million version of what was initially proposedβhas begun.
In fact, it got started in earnest at all but one of Fort Leeβs public schoolsβ, which was not included in the referendumβas soon as school got out for the summer.
Find out what's happening in Fort Leefor free with the latest updates from Patch.
And according to the school districtβs business administrator, this summerβs work, which will knock off about half of the 16 total projects approved when the referendum passed, is on track to be completed by the time school opens on Sept. 10, a week later than usual because of the construction and made possible by the district not using any snow days last year or having a February break.
Cheryl Balletto gave a presentation at Mondayβs school board meeting and provided a detailed progress report in an interview with Patch later in the week outlining whatβs been accomplished to date.
Find out what's happening in Fort Leefor free with the latest updates from Patch.
She said eight of the 16 projects included in the referendum are βon target for us to be able to open school on Sept. 10,β reporting the progress on those projects as follows:
The old boilers have been removed, and school officials expect delivery of new boilers by the end of this week or early next. In addition, every classroom slated to get new unit ventilators have had the existing ones removed.
Renovating the former central office space and converting it into four new classrooms has started.
βWe had a lot of asbestos removal at School 1 for that project,β Balletto said. βItβs all been removed. We got a passing mark from the state as well as the monitors that it was all removed properly.β
She said that work couldnβt start until June 22, when school got out and people could be restricted from the building, and that the contractor got it done in about a week.
βTheyβve already come in and done demolition and put up the framing for all four classrooms,β Balletto added. βStudents will be sitting in those classrooms on Sept. 10.β
βNormally the town runs a recreational camp, and normally they use School 1, but this year obviously they canβt because of the construction work so we let them use School No. 3 instead,β Balletto said. βWhat theyβve done so far is just remove the fence because the kids are using the back of the school to play and obviously in the building.β
She added that once the summer program is over at the school, workers will start in on masonry work on the building.
Workers have started in the back lot, doing some brick re-pointing and power washing to get the old grout out, according to Balletto.
The old boilers have been removed, and four new modular ones, which are much smaller, have been put in place. Balletto said the new boilers should prove to be βmuch more efficientβ in part because βyou donβt have to run all of them at one time.β
Masonry work on the buildingβs iconic clock tower is βin the process of being done,β Balletto said.
βTheyβve already mobilized; theyβve already been up there,β she said. βItβs amazing how fast they work.β
The pillars in front of the school have also been repaired; they just need to be painted, Balletto said Monday, and at the entrance to the cafeteria, the old bricks are being removed, and workers have started putting new bricks in.
In addition, air conditioning in the high school auditorium is being installed, which is why Mondayβs meeting was held in the high school library.
βThe vent has been delivered, and theyβve already started to demolish some of the ceiling to be able to put it in,β Balletto said.
All told, the work planned for this summer includes masonry work at the high school, School No. 3 and School No. 4; HVAC upgrades at the high school; boiler replacement at the middle school and School No. 1; and roof replacement at School No. 1 and the middle school.
Although those projects taken together represent half of the total projects called for in the referendum, Balletto said it will still take three summers to get everything done because some of the projects not planned for this summer are βmuch more time-consuming.β
She cited the middle school addition and new science labs at the middle school and high school as examples.
βWe canβt put all the labs out of commission,β Balletto explained. βWe still have to teach kids, and we have nowhere else to put them. So we might have to juggle that between two years.β
As for the selling of bonds to pay for the work, Balletto said school officials anticipate that will happen at the end of July or the beginning of August, and that she hopes to be able to announce details at the next school board meeting on July 23 after consulting with the districtβs bond counsel.
****
Find us on Facebook or Twitter, or for news straight to your inbox, sign up for our daily newsletter.
Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.
