Whitpain Township's Road Resurfacing Program in Third and Final Phase

Whitpain township began the third and final phase of their 2013 road resurfacing program on Tuesday, which is an extension of their 2012 resurfacing program.

The six-day phase will commence on July 23 with the resurfacing of Hickory Road, Kurt Road, and Second Road.  In 2013 Whitpain will have resurfaced over 10 miles of roads, said Ronald Cione, director of the Public Works department.

The second phase was completed last week, using an environmentally-friendly technique.  Once the workers finish during the next week, the township will start preparing next year’s roads next month.

Find out what's happening in Lower Gwynedd-Ambler-Whitpainfor free with the latest updates from Patch.

“I would be hard-pressed to find a pothole on a single township road,” said Whitpain treasurer Frederick R. Conner, Jr., at the July 16 Board of Supervisors meeting.

 

Find out what's happening in Lower Gwynedd-Ambler-Whitpainfor free with the latest updates from Patch.

Following is a list of the roads affected:

July 16

Midway Lane

Rosemarie Lane

Johns Road

Doans Way

 

July 17

Laurence Drive

Valley Road

Hoover Road

 

July 18

Boxwood Road

White Oak Road (Hemlock Road to Hemlock Road)

Butternut Road

Sycamore Road

 

July 19

Ginko Drive

Beechnut Road

Juniper Road

White Oak Road (Hickory Road to Pheasant Meadow Road)

Larch Road

 

July 22

Hemlock Road

 

July 23

Hickory Road

Kurt Road

Second Road

 

The township notes that all work is weather-permitting.

 