Politics & Government

Canwood Street Improvement Construction Schedule for Next Two Weeks

The following information from the City of Agoura Hills website is the construction schedule and traffic information for the Canwood Street Improvements.

Construction Schedule: June 10-June 21

Week of June 10th - Reconstruction of pavement section on the south side of Canwood, between Forest Cove and Strawberry Hill, continues. Traffic Detour continues to be in place. Additional areas of sidewalk will be removed and replaced towards the end of the week.

Week of June 17th - Roadway widening east of Fire Station will begin.

TRAFFIC CONTROL


Please be aware that the following traffic controls will be expected for the Canwood Street Improvements project (Please see photo).

Find out what's happening in Agoura Hillsfor free with the latest updates from Patch.

Phase 1a/1b is expected to be in place from the first week of May until early June. Eastbound traffic will be closed from Forest Cove to Strawberry Hill and a detour will be in place.

Phase 2a/2b is expected to be in place during the 1st week of June. Expect traffic to be controlled by flaggers during working hours. Both lanes of traffic will be open after working hours.

Find out what's happening in Agoura Hillsfor free with the latest updates from Patch.

Phase 3, 4 and 5 is expected to be in place from Mid-June to Early July. Expect traffic to be controlled by flaggers during working hours. Both lanes of traffic will be open after working hours.

Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.