A large piece of construction machinery fell into a dredged area  of the San Francisco Bay near Bair Island on Monday afternoon.

A piling machine with a 60-foot mast overturned on its side while  working to install a 48-inch sewage transmission pipeline at about 4 p.m.,  South Bayside System Authority Manager Dan Child said.

No one was injured in the incident, Child said. The mast landed outside the construction zone, but did not come in  contact with sensitive habitat in the marsh area of Bair Island, Child said.

A small amount of diesel fuel leaked onto soil, which was cleaned  up and removed from the site, he said. On Tuesday afternoon crews were continuing to work to remove the  fallen equipment and work on the pipeline replacement had been temporarily
suspended.

The pipeline installation near Bair Island is part of a $45.5
million project to replace a portion of aging sewer main that runs between
Menlo Park and a treatment facility in Redwood Shores.