Route 83, Winchester Road Intersection Reopens After Months Of Construction Work
The upgraded intersection now includes a new traffic signal with left and right turn lanes and a realigned intersection.
GRAYSLAKE, IL — The Lake County Division of Transportation has reopened the intersection of Winchester Road and Route 83 following months of construction on a safety-focused improvement project.
The upgraded intersection now includes:
- A new traffic signal with left and right turn lanes
- A realigned intersection that improves visibility and enhances safety
- Drainage improvements that will reduce flooding on IL Route 83
- Enhanced soil stability to support the reconstructed roadway
The intersection was originally scheduled to reopen in October after it was closed in July. However, once construction began, crews discovered a larger-than-expected area of poor soil (peat) south of the intersection, according to a news release from IDOT.
Find out what's happening in Crystal Lake-Caryfor free with the latest updates from Patch.
This required additional groundwork to ensure a safe, stable road base. While this extended the project by about two months, LCDOT prioritized long-term safety and durability.
LCDOT thanks its contractors and project partners for their work to reopen the intersection before the end of the year. Most of all, LCDOT appreciates the public’s patience during a longer-than-expected construction timeline.
Winter has arrived. Use Lake County PASSAGE before you hit the roads to see the latest road conditions.
Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.