Politics & Government

Green Line Extension Completion Pushed Back to Between 2018 and 2020

Plans to extend the Green Line through Somerville to Medford have been pushed from 2015 to 2018 - or as late as 2020.

It's going to take at least a few more years than anticipated to complete the Green Line Extension project, the Massachusetts Department of Transportation announced Monday.

Following a four-month-long cost and schedule analysis, the Green Line Extension project team decided the completion of the project, previously projected for October 2015, will take until fall of 2018 at the earliest, according to a Department of Transportation press release.

According to a status report issued by the Department of Transportation, it's more likely the project will take until summer of 2020.

Find out what's happening in Somervillefor free with the latest updates from Patch.

Timeframe
According to the status report, "MassDOT and the MBTA now have a much deeper and more nuanced understanding of the constraints and limitations that must be managed in order to implement the Green Line Extension project."

The report continues to say, "We are now projecting a timeframe ... for the introduction of revenue service on the Green Line Extension. The points within the timeframe are associated with different probabilities, as shown below:

Find out what's happening in Somervillefor free with the latest updates from Patch.

  • 10% Probability of Not Exceeding – September 2018
  • 50% Probability of Not Exceeding – June 2019
  • 90% Probability of Not Exceeding – July 2020"

Funding challenges
The MassDOT status report names funding as one of the major obstacles faced by the planned Green Line Extension. The project is seeking federal funding as part of the Federal Transit Administration's New Starts program, the MassDOT status report says.

"The challenges related to the New Starts process—a complex, demanding, and time-consuming process—have added substantial time to the schedule for initiating design of the Green Line Extension project," the report says.

The Commonwealth of Massachusetts is committed to funding the Green Line Extension with money from transportation bonds, according to the report, but the ongoing costs of operating the Green Line Extension, which would be fall on the shoulders of the cash-strapped MBTA, could hurt the project's chances for federal New Starts funding.

"[T]here will be ongoing operating expenses associated with running the expanded Green Line that must be borne by the MBTA. We are therefore concerned about the effect that the enormously constrained financial condition of the MBTA system will have on our chances of success within the New Starts program," the report says. 

Phasing scenario
In an effort to speed up implementing the extension, MassDOT and the MBTA are considering a "phasing" scenario that would allow for some stations to open for public use while others are still being constructed, the press release said. It did not specify which stations would be first to open.

The project will extend the Green Line from it's current final northbound stop at Lechmere in Cambridge through East Somerville, with a final stop at the intersection of College Avenue and Boston Avenue in Medford. A total of seven stops will be installed at a projected cost of $1 billion.

A possible second phase of the project would continue the line from College Avenue to Mystic Valley Parkway near the Medford/Somerville line.

The new time range for completion is contingent on the MBTA taking full ownership of property required for construction, the press release said.

Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.