Here is an updated schedule of road construction projects in the town of Westwood.

Here is a look at the latest update on road construction projects in Westwood, according to Director of Public Works Todd Korchin.
Hartford/Burgess/Oriole neighborhood/Woodland Road
- On schedule to be paved as soon as the casting crews have completed their adjustments. Timeline for paving is the end of next week (Aug. 12-16) into the following week (Aug. 19-23).
High Rock/Dover Road/Conant Road Traffic Calming
Find out what's happening in Westwoodfor free with the latest updates from Patch.
- Milling and prep work along with sign installations next week (Aug. 12-16). Expect detours and closures along routes this week (Aug. 5-9)
- Structures will be installed the week of Aug. 19-23. Expect Detours/Closures along routes this week.