Milling, Paving Schedule Announced For Chester Roadways

More than a dozen paving/milling projects are scheduled in Chester over the next few weeks.

CHESTER TOWNSHIP, NJ — Chester officials have announced the schedule for its upcoming milling and paving roadway projects. There are several projects planned, which will be done over the next few weeks.

The paving and milling will begin on Wednesday and is expected to be completed in early September. See the schedule for milling, paving, and micro milling below, provided by Chester Township:

Milling

Find out what's happening in Mendham-Chesterfor free with the latest updates from Patch.

  • Aug. 20 — Woodhull Dr & Cromwell Dr
  • Aug. 21 — Cromwell Dr, Topping Way, Wood Stone Rd
  • Aug. 22 — Bird Song Ct, South Gables
  • Aug. 25 — South Gables, Tigerbrook Ln, Long Hill Rd, East Fox Chase Rd
  • Aug. 26 — East Fox Chase, Ashland Ter
  • Aug. 27 — Ashland Ter, Park Ridge, Benjamin Dr
  • Aug. 28 — Benjamin Dr, Fredrick Pl
  • Aug. 29 — Benjamin Dr

Paving

  • Aug. 25 — Topping Way, Woodhull Dr, Cromwell Dr
  • Aug. 26 — Cromwell Dr, Wood Stone Rd, South Gables Dr
  • Aug. 27 — Birdsong, S. Gables Dr
  • Aug. 28 — S. Gables, Benjamin Rd, Fredrick Pl
  • Aug. 29 — Benjamin Rd, Tiger Brook Ln
  • Sept. 2 — Tiger Brook Ln, Ashland Ter, Park Ridge
  • Sept. 3 — Ashland Ter, East Fox Chase Rd, Long Hill Rd

Micro milling will take place on Aug. 22 on the following roadways:

Find out what's happening in Mendham-Chesterfor free with the latest updates from Patch.

  • Deer Hill Ct
  • Red Oak Row
  • Runyan Pl
  • Patrey Ct
  • Craig Ln

Officials added that these dates are subject to change, depending on weather or other factors.