LIRR: Smoother Ride for Customers as Track Work Wraps Up Friday

More than 17,000 railroad ties were replaced between Huntington and Port Jefferson.

ong Island Rail Road commuters should be able to enjoyΒ a smoothΒ as trackΒ work on the Port Jefferson Branch wraps up on Friday.Β 

The LIRR will haveΒ installed moreΒ than 17,000 newΒ railroad ties between the Huntington and Port Jefferson stations on the Port Jefferson Branch between June 24 and Aug. 9. Normal trainΒ service is expected to resume after Friday.Β 

"The work on the Port Jefferson Branch will help ensure safety, greater service reliability and a smoother, more comfortable ride for customers," read an LIRR release.Β 

Aaron Donovan, LIRR's deputy director for external communications, said crews have installedΒ 12,000 concrete ties along 4.5 miles of track between Kings Park and Port Jefferson.Β 

"This means the majority of the rails along this stretch are now concrete ties, which last longer and provide a steadier, smoother ride," Donovan said.Β 

LIRR crews also replacedΒ 5,200 wood ties between Huntington and Kings Park stations. Β In doing so, crews eliminated railroad joints and regraded the tracks, according to Donovan.Β 

Other changes to the tracks includeΒ renewing six railroad crossings between Huntington and Port Jefferson, andΒ replacingΒ bridge timbers on the LIRR bridge over Old Town Road in Setauket.Β 

These projects are part of the $70 million the LIRR reports isΒ budgeted for 2013 to help maintain the railroad's infrastructure.Β 