Bear Mountain Parkway Project: What to Expect, When

Folks who attended Thursday's meeting on the Bear Mountain Parkway Project--which aims to improve safety on the roadway in Cortlandt and Peekskill--learned scheduling details of the construction process.

Here is the timeline officials provided:

- Variable message signs installation: Complete

-Survey and stakeout: Ongoing

-Turn lanes, milling and paving, permanent pavement markings, curbs and regulatory signs: September 2013 to Oct. 31, 2013*

-Box beam median barrier and guide rail: October 2013 to Dec. 13, 2013

-Signal improvements at Carhart Lane: October 2013 to May 15, 2014

-All work complete: May 15, 2014


--

* indicates some night work (dates will be announced via variable message signs)