I-90 Lane Restrictions, Closures Could Impact Westlake Drivers
With Labor Day weekend upon us, there are plenty of travel plans in motion...and plenty of roadwork to slow you down.

WESTLAKE, OH — Labor Day weekend took a long time to arrive, though Ohioans planning holiday weekend trips may need a bit more patience.
The Ohio Department of Transportation has plans to continue roadwork on all of the Buckeye State's major highways. For Cleveland's west side residents, we've compiled a list of the projects most likely to impact you this weekend.
Here's some of the roadwork that could impact your holiday weekend, according to ODOT:
Find out what's happening in Westlakefor free with the latest updates from Patch.
- I-90 bridge reconstruction
I-90 eastbound and westbound at the structures over the railroad tracks, between French Creek Road and SR 611 (Colorado Avenue), will have lane closures. Traffic will be maintained with barrels and portable concrete barriers. Traffic will be maintained in 11 foot lanes eastbound and westbound. Speed limits will be established at 55 mph for areas with barrier wall and 50 mph for areas with barrels when workers are present. Estimated completion: July 2022
- I-480 resurfacing
I-480 eastbound and westbound, between the Ohio Turnpike (I-80) and Lorain Road, will have daily and nightly lane closures for a resurfacing project. Estimated completion: September 2021
Find out what's happening in Westlakefor free with the latest updates from Patch.
- I-90 bridge repairs in Rocky River and Lakewood
There will be nightly lane restrictions through October as crews repair the bridge.
- U.S. Route 6 (Detroit-Superior) bridge
Crews are doing bridge repairs between W. 9th St. and W. 25th St. Work will close Merwin Avenue between Center St. and West St. bridge. Work should be completed on this project in October.
- I-90 bridge rehabilitation in Cleveland
Crews will rehabilitate and paint bridges on I-90 between E. 136th and E. 156th, E. 140th and E. 152nd on I-90 in Cleveland. Work should be finished in July 2022.
As part of that work, the E. 140th ramp to I-90 east will be closed through late September. Drivers will detour along S. Waterlood Road to I-90 east.
E. 152nd and E. 140th Street, under I-90, and connector roads between the streets, will have off-peak lane closures and restrictions.
- I-90 interchange improvements
The Ohio Department of Transportation is improving traffic flow on Martin Luther King Jr. Drive, at the I-90 interchange. The area will have various daily lane restrictions.
- Grayton Rd. over I-480 bridge deck replacement
Bridge deck replacement on the Grayton Rd. bridge over I-480 in Cleveland. Work should be finished in mid-October 2021.
- Paint the I-480 bridge over the Rocky River and SR 10
SR 10 east and west will have various lane restrictions through at least November. Work should be finished on this project in June 2022.