Avery Hill Road Update
The work is complete except for final centerline striping. This is planned for later in the week of October 21st, weather permitting.
Vinegar Hill Road and Washington Drive
Paving is complete. Driveway apron work for this project is scheduled to begin on Monday, October 21st, with completion sometime the week of October 28th. Any traffic impacts should be minor. Centerline striping of Vinegar Hill Road is planned for later in the week of October 21st, weather permitting.
Blonders Boulevard
Paving of this road is presently scheduled as a one-day event sometime the week of October 28th. A specific date will be given when known.