Work will begin this week on the Branchville Transit Oriented Development Plan.
RIDGEFIELD, CT — Work will begin this week on the Branchville Transit Oriented Development Plan.
The project aims at bringing new sidewalks, lighting, landscaping, and improved access for pedestrians to businesses in the Branchville Area.
Work near the intersection of Routes 102 and 7 and the Branchville Train Station is on tap for the week of April 24, according to the latest update from the Town of Ridgefield.
Find out what's happening in Ridgefieldfor free with the latest updates from Patch.
- Tuesday, April 25: Onsite Services will be installing construction signage starting at 9 a.m. and finishing at approximately 3 p.m.
- Wednesday, April 26: McLellan Tree Clearing will perform clearing and grubbing starting at 7 a.m. and finishing at approximately 3 p.m.
- Thursday, April 27 and Friday, April 28: J. Iapaluccio will perform construction staking
- Monday, May 1: Berkshire Concrete Cutting will saw cut roadways starting at 7 a.m. and finish at approximately 3 p.m.