Route 74 Bridge In Tolland Slated For Re-Opening Next Week

The Route 74 bridge re-opening is slated for next week in Tolland.

On Tuesday, there will be no more road closed signs at the Route 74 bridge over the Skungamaug River, state DOT officials said.
On Tuesday, there will be no more road closed signs at the Route 74 bridge over the Skungamaug River, state DOT officials said. (Chris Dehnel/Patch )

TOLLAND, CT — Connecticut Department of Transportation officials Tuesday said the re-opening the of the Route 74 bridge over the Skungamaug River is planned for Aug. 6.

The bridge is located near the Route 74-Skungamaug Road intersection. The bridge was closed on May 6 and the re-opening date represents two days earlier than the original estimated opening.

"The road opening signifies a substantial milestone on the project associated with a bridge replacement carrying Route 74 over the Skungamaug River," DOT officials said.

Find out what's happening in Tollandfor free with the latest updates from Patch.

Officially dubbed CTDOT Project No. 0142-0152, the work for a new bridge to replace the aging span was awarded to ROTHA Contracting Company, Inc. at a cost of $4,779,424.50 on Aug. 16, 2023.

After the opening, motorists can expect one-way alternating traffic until the remaining construction and utility work activities are completed, DOT officials said. The lane closures may occur Monday to Friday from 8 a.m. to 4 p.m., according to the DOT.