The following is a traffic alert on road construction projects from the Town of Framingham and MassDOT for the week of June 29 to July 4.

The following is a traffic alert on road construction projects from the Town of Framingham and MassDOT for the week of June 29 to July 4.
CENTRAL STREET BRIDGE OVER THE SUDBURY RIVER: Major demolition and reconstruction of the bridge will continue. Traffic will continue to be detoured over the Wickford Road Bridge. Please allow additional travel time.
COBURN STREET AREA: The contractor will begin storm drain installation on Bridges Street and Naples Street and water hydrant relocations on Hilton Street and Bethany Road. Expect minimal delays.
Find out what's happening in Framinghamfor free with the latest updates from Patch.
CONCORD STREET (Between Hartford Street and Route 9) Sidewalk removal and restoration work will continue. Expect minimal delays.
CONCORD STREET (Route 126) DOWNTOWN FRAMINGHAM RECONSTRUCTION: The MassDOT contractor will continue street light foundations north of the railway crossing. Expect moderate delays and on-street parking restrictions.
Find out what's happening in Framinghamfor free with the latest updates from Patch.
DANFORTH STREET: One contractor will be working on sewer main replacement in the area of Sudbury Landing. Another contractor will be working on sidewalks and casting adjustments. in preparation for final paving Tuesday, June 30. Seek alternate route. Expect delays.
EVERSOURCE DOWNTOWN UTILITY PROJECT: The contractor will continue night work Monday through Friday evening, from 7 p.m. to 5 a.m. on Union Avenue from Pearl Street to the rotary. Expect moderate delays.
HEMENWAY ROAD AREA: Roadway surface preparation work will begin. Expect minimal delays.
HERBERT STREET/IRVING STREET/LORING DRIVE: Contractors will be performing sidewalk work on Irving Street and Loring Drive as well as manhole work . Expect moderate delays.
MAIN STREET: The contractor will continue to install new water main along Main Street from Walnut Street to Union Avenue. A detour will be in place on this section of the roadway. Please seek alternate route. Expect delays.
OLD WORCESTER ROAD AREA: Roadway surface preparation work will continue, a hot mix asphalt leveler course will be applied and casting adjustments will be made. Expect minimal delays.
ROUTE 9 BRIDGE OVER FOSS RESERVOIR OUTLET: No lane closures expected for motor vehicles; however, the pedestrian sidewalk on the westbound side of Route 9 will be closed. Expect minimal traffic delays.
SALEM END ROAD: Final adjustments. Loaming and seeding. Expect minimal delays.
WATER STREET: The contractor will continue work on the retaining wall on the east side of Water Street. Expect minimal delays.
WINTER STREET BRIDGE OVER CSX: The MassDOT contractor will continue work on the temporary sewer bypass and prepare the site for construction to begin. Expect minimal delays.
Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.