Where You Will Encounter Road Construction This Week in Framingham
Hemenway Road, Concord Street, Newbury Street and Old Worcester Road are among the town and state projects.

Below is a list of where you will find road construction projects in Framingham. The projects are a combination of Town of Framingham and MassDOT projects.
CENTRAL STREET BRIDGE OVER THE SUDBURY RIVER: Major demolition of the bridge will continue. Traffic will continue to be detoured over the Wickford Road Bridge. Please allow additional travel time.
COBURN STREET AREA: The contractor will be mobilizing and installing construction signage and videoing both the surface of the project and the sewer mains. Expect moderate delays.
Find out what's happening in Framinghamfor free with the latest updates from Patch.
CONCORD STREET (Route 126) DOWNTOWN FRAMINGHAM RECONSTRUCTION: The MassDOT contractor will continue street light foundations and sidewalk work on Hollis Street. Expect minimal delays.
DANFORTH STREET: One contractor will be excavating and prepping sidewalks and removing and resetting sidewalk curbs. A second contractor will continue sewer replacement between Kings Court and Sudbury Landing. Traffic will be reduced to a single lane in the one-way portion area. Expect minimal delays.
Find out what's happening in Framinghamfor free with the latest updates from Patch.
EVERSOURCE DOWNTOWN UTILITY PROJECT: The contractor will continue night work Monday through Friday evening, from 7:00 p.m. to 5:00 a.m. on Concord Street between Sanger Street and the rotary and on Union Avenue from Pearl Street to the rotary. Expect moderate delays.
HEMENWAY ROAD AREA: Roadway surface preparation work will begin. Expect minimal delays.
HERBERT STREET/IRVING STREET/LORING DRIVE: Contractors will be working on installing a sewer manhole and sewer pipes at the intersection of Irving Street and Herbert Street. A second crew will be installing conduit on Irving Street from Blandin Avenue to the intersection of Herbert Street. Expect moderate delays.
MAIN STREET: The contractor will mobilize to install new water mains from Route 9 heading west towards Walnut Street. Expect moderate delays.
MELLEN STREET: The contractor will be addressing final punch list items. Expect minimal traffic delays.
NEWBURY STREET: The contractor will continue sidewalk forms and finish work. School buses will be given priority. Expect moderate delays.
OLD WORCESTER ROAD AREA: Roadway surface preparation work will continue and a hot mix asphalt leveler course will be applied. Expect minimal delays.
RIVERPATH DRIVE/OLD CONNECTICUT PATH: The contractor will continue landscaping and sign installations. Expect minimal delays.
ROUTE 9 BRIDGE OVER FOSS RESERVOIR OUTLET: No lane closures expected for motor vehicles; however, the pedestrian sidewalk on the westbound side of Route 9 will be closed. Expect minimal traffic delays.
SAXONVILLE INTERSECTION IMPROVEMENT PROJECT: In the area of School Street and A Street minor sidewalk work will take place. Expect minimal delays.
WATER STREET: The contractor will continue work on the retaining wall on the east side of Water Street. Expect minimal delays.
WHITTIER STREET: The contractor will conduct miscellaneous sidewalk and curb work in the area. Seek alternate route. Expect minimal delays.
WINTER STREET BRIDGE OVER CSX: The MassDOT contractor will continue work on the temporary sewer bypass and prepare the site for construction to begin. Expect minimal delays.