Newton Bus Route Slated for Changes, Improvements in July, August

The MBTA has announced upgrades and improvements to 15 "Key Bus Routes," which includes one route that services Newton.

The MBTA Monday announced the beginning of consturction for its Key Bus Routes Improvement Program, which will impact 15 bus routes throughout the service area during the summer months.

The selected 15 routes are the busiest in the network, according to an MBTA press release, and service about 885 bus stops in eight communities, including Newton.

Route 57, which services several stops in Newton Corner enroute between Watertown Yard and Kenmore Square, is scheduled to receive the improvements from July 15 to Aug. 30.

Find out what's happening in Newtonfor free with the latest updates from Patch.

According to a press release from the MBTA, the Key Bus Routes Improvment Program is intended to "improve the overall quality of service for the bus-riding public by making improvements and adjustments to both physical characteristics and service."

Improvements will include consolidating bus stops and reducing them by 25 percent, which is expected to reduce trip times by 13 percent. Currently, many bus stops are visible to one another, the pres release reads.

Find out what's happening in Newtonfor free with the latest updates from Patch.

Additional work will included making stops ADA accessible and improving or adding amenities such as shelters, benches, trash barrels and signage.

"The MBTA is looking forward to improving the quality of amenities and service on some of our most utilized services,” said MBTA General Manager Beverly Scott said. "This aggressive and ambitious project will reduce trip times, enhance customer comfort, accessibility, convenience and safety, and make service more reliable and cost-effective."

The work is being completed as part of $10 million American Recovery and Reinvestment Act (ARRA) grant.

The first set of routes to undergo improvements as the project begins this week include routes 22, 23, 28 and 32. The full projected schedule of work to be completed is below:

Projected Work Dates for Key Bus Routes

Route 1 – July 1 – July 25

Route 15 – June 24 – July 12

Route 22 – June 17 – July 17

Route 23 – June 17 – July

Route 28 – June 17 – Aug. 30

Route 32 – June 24 – Aug. 8

Route 39 – July – August

Route 57 (services Newton) – July 15 – Aug. 30

Route 66 – June 24 – Aug. 1

Routes 71-73 – Aug. 1 – Aug. 30

Route 77 – July 25 – Aug. 26

Route 111 – Aug. 9 – Aug. 30

Routes 116/117 – July 19 – Aug. 30