Summary of the May 28, 2024 GPW Plan Commission
Friendship Factory, Nino Salvaggio's Cafe, and Crispelli's among projects discussed

Project discussed during the May 28, 2024 Plan Commission meeting included:
- Friendship Factory (20100-20102 Mack Avenue):
- The site plan was approved with conditions including traffic markings, dedicated drop-off/pick-up spaces, and compliance with signage and rubbish storage requirements. The project targets an August 2024 opening.
- Nino Salvaggio’s Café (20331 Mack Avenue):
- Approval was granted for interior and exterior renovations to open a market-style café. Conditions included compliance with lighting standards, wall signage, trash receptacle management, and protective barriers for outdoor dining.
- Crispelli’s Outdoor Café:
- The commission discussed and approved the site plan amendment for an outdoor café at Crispelli’s. Conditions included the addition of decorative planters and compliance with sidewalk and patio hardscape requirements.
- Crosspointe Christian Church Project:
- Construction has begun with footings installed. The architect is addressing life safety inquiries from the fire inspector. The project is progressing well.
- Hungry Howie’s Interior Renovations:
- Building permit applications have been submitted for interior renovations.
- 694 Peach Tree Lane:
- The project is nearing completion with a deadline for the final grade as-built drawing submission by the end of the month.
- 707 N. Renaud:
- The project is extended to mid-August due to long lead times for certain items, with expected completion by then.
This summary was generated from the Plan Commission meeting packet by ChatGPT.