MnDOT Finishes I-94 Work From Maple Grove To Rogers After 2 Years
Traffic is now flowing in three lanes in each direction, with a fourth soon to open between Maple Grove and Rogers, according to a report.

MAPLE GROVE, MN — Minnesota transportation officials on Friday marked the imminent end of a two-year construction project on I-94 between Maple Grove and Rogers.
Traffic is now flowing in three lanes in each direction, with a fourth soon to open along that portion of the interstate, the Star Tribune reports.
That 11-mile stretch remains a work zone, as crews still have to complete some tasks, meaning the speed limit will stay at 60 through the end of November, the report states.
Find out what's happening in Maple Grovefor free with the latest updates from Patch.
$20 No-Show Fee For Drivers Who Miss Road Test Appointment: DVS
Drivers face fines of up to $300 for speeding in work zones, according to the Minnesota Department of Transportation.
Find out what's happening in Maple Grovefor free with the latest updates from Patch.
More than 700 crashes have been reported along that stretch of I-94 since the project started in 2019, including one fatal crash and three that caused serious injuries, the Star Tribune reports.
Twelve people have died in construction zones this year in Minnesota, CCX Media reports.
8 Maple Grove Schools Remain On MDH Coronavirus Outbreak List
MnDOT Commissioner Margaret Anderson Kelliher said the interstate will be “smoother, safer and better” thanks to the improvements made over the last two years, the report states.
The $127 million project also included nine miles of new road and some improvements at intersections where local roads connect to the interstate, CCX Media reports.
The construction between Maple Grove and Rogers is part of a $350 million project to repair roads and add lanes on I-94 from Maple Grove to Clearwater.