Road work is scheduled to start on Monday next week and run through Friday. Here's what you need to know:

MARLBORO, NJ — Road work is scheduled to take place throughout Marlboro next week, Marlboro Township announced Friday evening.
According to a road construction notice from Marlboro Township, road work will begin on Monday night and continue through Friday. Roads will be closed during construction hours, officials said, with police present and a detour in place.
Here's what you need to know:
Find out what's happening in Marlboro-Coltsneckfor free with the latest updates from Patch.
Monday, Aug. 19
Officials said the contractor’s crew will be on Harbor Road performing drainage improvements between Henry Hudson Trail and Route 79 from 7 a.m. to 4 p.m.
Find out what's happening in Marlboro-Coltsneckfor free with the latest updates from Patch.
Tuesday, Aug. 20
The contractor’s crew will be on Harbor Road to perform drainage improvements between the Henry Hudson Trail and Route 79 from 7 a.m. to 4 p.m.
Wednesday, Aug. 21
The contractor’s crew will be on Harbor Road to perform drainage improvements between the Henry Hudson Trail and Route 79 from 7 a.m. to 4 p.m.
Thursday, Aug. 22
From 7 a.m. to 4 p.m., New Jersey Natural Gas will be on School Road East performing gas main replacement between Warren Drive and Oak Lane.
Friday, Aug. 23
From 7 a.m. to 4 p.m., New Jersey Natural Gas will be on School Road East performing gas main replacement between Warren Drive and Oak Lane.
In addition to work on School Road East, the contractor’s crew will be on Lloyd Road to perform mill and pave operations between Route 79 and the Aberdeen border from 6 p.m. to 6 a.m.