Traffic & Transit
Construction Coming Up On Morristown Streets: See When
Milling and paving work will start July 8 on some of Morristown's streets, including Maple and MacCulloch Avenues. Here's the schedule:

MORRISTOWN, NJ —Morristown public safety officials are giving residents a heads-up about milling and paving on some town streets, which is scheduled to last about a week.
The PSE&G-contracted work is slated to begin on Monday, July 8 and last through Monday, July 15, to remove part of the road surface and put fresh pavement down.
Here are the affected streets, and estimated project dates. Drivers may experience detours and road closures.
Find out what's happening in Morristownfor free with the latest updates from Patch.
Maple Avenue between Miller Road and James Street
- Milling date: July 8
- Paving date: July 11
Perry Street between Maple Avenue and Macculloch Avenue
Find out what's happening in Morristownfor free with the latest updates from Patch.
- Milling date: July 8
- Paving date: July 11
Madison Street between Green Street and South Street
- Milling date: July 9
- Paving date: July 11 and 12
Green Street between James Street and Madison Street
- Milling date: July 9
- Paving date: July 12
James Street between South Street and Ogden Place
- Milling date: July 10
- Paving date: July 12
Green Hill Road between Franklin Street and Revere Road
- Milling date: July 11
- Paving date: July 15
Revere Road between Franklin Street and the dead end
- Milling date: July 11
- Paving date: July 15
Altamont Court to Elm Street
- Milling date: July 11
- Paving date: July 15