Atlantic Yards-Area Civic Groups: 'We Need More Contractors'
Brooklyn Speaks says dividing up the project could shorten construction from 25 years to 10.

A coalition of Atlantic Yards-area civic groups are urging state officials to consider the idea of bringing in additional developers to speed construction at Atlantic Yards.
Brooklyn Speaks issued a news release on the issue Wednesday morning in advance of a public hearing on Atlantic Yards construction that night.
At issue is a 2009 decision by Empire State Development, the state agency overseeing Atlantic Yards Construction, to allow developer Forest City Ratner to change the length of construction on the project from 10 years to 25 without conducting a new community impact study (called an SEIS) on how the construction would affect the surrounding community.
Find out what's happening in Carroll Gardens-Cobble Hillfor free with the latest updates from Patch.
Brooklyn Speaks, Develop Don’t Destroy Brooklyn and others sued, arguing that a 25-year construction site would have a very different impact than one that lasts only 10 years.
The Brooklyn Speaks coalition won the initial suit and several appeals.Â
Find out what's happening in Carroll Gardens-Cobble Hillfor free with the latest updates from Patch.
Wednesday night's hearing is on the new SEIS, which Brooklyn Speaks argues doesn't consider ways to shorten construction, such as their suggestion to bring in more contractors.Â
The group also argues that the study doesn't address the delays in the benefits promised by the project including affordable housing, jobs and open space.Â
“Atlantic Yards was approved on the basis of removing blight conditions in and around the Vanderbilt rail yards,” said Jo Anne Simon, Democratic District Leader of the 52nd A.D., in a release. “Instead, the project has actually created blight by demolishing buildings, displacing residents and businesses, and causing massive disruptions for the project’s neighbors across its 22-acre site. It’s outrageous that ESDC would fail to even consider how a decade or more of delay could be avoided.”
Joe DePlasco, a spokesman for Forest City Ratner, said via e-mail that the developer is building the project "as fast as possible" and has already begun work on the first residential building.Â
"There are also other benefits that have been delivered, including the rail yard and quite a bit of infrastructure work. There were of course significant delays because many of the people who are now saying it is too slow were involved in delaying the project," he said.
A spokesman for Empire State Development said via e-mail that "Brooklyn Speaks' comments and suggestions will be considered as part of the public scoping process and responded to in the final scope document."