Blair Mill Road Widening Project Resumes
Horsham Township officials said Phase II of the widening of the key road will start up again at the end of the month or by early July.

HORSHAM TOWNSHIP, PA — After 26 months, Phase II of the Blair Mill Road widening project is back on track.
Horsham Township officials said that over 20 utility companies have finished relocating their utilities, meaning that road construction can finally resume.
"It’s a beautiful sight…empty telephone poles," township officials said.
Find out what's happening in Hatboro-Horshamfor free with the latest updates from Patch.
Township officials said the project's contractor will be back for road construction by the end of June or early July.
Road construction is expected to be completed by the end of the year, with landscaping, restoration, and punch list items getting taken care of next spring.
Find out what's happening in Hatboro-Horshamfor free with the latest updates from Patch.
Phase III, the final phase of the project, is in the design, engineering, and permitting stages, officials said.
When Phase III is completed, by the end of 2030, Blair Mill Road will be five lanes from Welsh Road to Easton Road, officials said.
The roadwork will also include intersection improvements at Easton Road and Blair Mill Road.
"Over the coming months, we will notify you about any lane restrictions in advance," officials said. "We understand your frustration, and we thank you for your patience."