Traffic & Transit
PECO Underground Pipe Replacement Begins In Horsham
PECO is expected to perform the work into August in a section of Horsham. The work starts Monday. Find out where below.

HORSHAM TOWNSHIP, PA —PECO will begin a pipe replacement project in a section of the township starting Monday and running into August, township officials said.
PECO will be replacing the existing natural gas equipment to enhance service in a neighborhood. This includes installing a new underground pipe, which is more durable, enhances safety, and improves service reliability.
Work is expected to begin on July 8 in the area of Witmer Road between Dresher Road and Prudential Road.
Find out what's happening in Hatboro-Horshamfor free with the latest updates from Patch.
Work will be performed Monday through Friday from 7 a.m. – 3 p.m.
The project is expected to be completed in August 2024.
Find out what's happening in Hatboro-Horshamfor free with the latest updates from Patch.
The work will be performed by Riggs Distler, a qualified PECO contractor.
Anyone with questions or to schedule an appointment should contact Dave Zwizanski of Riggs Distler at 609-941-2115.
Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.