Traffic & Transit
'Risk Of Collapse' Evaluation Ordered For WI Bridge
The NTSB is recommending 68 bridges — including one in Wisconsin — undergo a vulnerability assessment to determine the risk of collapse.

GREEN BAY, WI — As the National Transportation Safety Board continues its investigation into the deadly collapse of the Francis Scott Key Bridge in Maryland, the safety administration has identified numerous bridges that are also at risk of collapse should a vessel collide with them.
As a result of the investigation, the NTSB is recommending that 68 bridges — including one in Wisconsin — undergo a vulnerability assessment to determine the risk of collapse.
The NTSB this week released a report on the March 2024 Maryland incident that documented dozens of other bridges across the nation they say have "unknown levels of risk of collapse" from vessel collisions.
Find out what's happening in Green Bayfor free with the latest updates from Patch.
The Leo Frigo Memorial Bridge — located on the north side of Green Bay — was recommended to undergo a risk assessment.
The Leo Frigo Memorial Bridge was deemed a "critical/essential" bridge.
Find out what's happening in Green Bayfor free with the latest updates from Patch.
The NTSB is recommending the Wisconsin Department of Transportation calculate the annual frequency of collapse for the structures using the Method II calculation from the American Association of State Highway and Transportation Officials.
If a bridge exceeds that risk threshold, it is considered high risk, according to NTSB. The owners must inform the NTSB whether the probability of collapse is above the threshold.
"Today’s report does not suggest that the 68 bridges are certain to collapse. The NTSB is recommending that these 30 bridge owners evaluate whether the bridges are above the AASHTO acceptable level of risk. The NTSB recommended that bridge owners develop and implement a comprehensive risk reduction plan, if the calculations indicate a bridge has a risk level above the AASHTO threshold," the NTSB said.
A date by which the assessments must be complete was not immediately clear.
Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.