Emergency Sewer Repairs Set For Buena Vista Avenue In Alameda

In October, the East Bay Municipal Utility District will begin emergency sewer repairs along segments of Buena Vista Avenue in Alameda.

In October, the East Bay Municipal Utility District will begin emergency sewer repairs along segments of Buena Vista Avenue in Alameda.
In October, the East Bay Municipal Utility District will begin emergency sewer repairs along segments of Buena Vista Avenue in Alameda. (Scott Anderson/Patch)

ALAMEDA, CA -- In October, the East Bay Municipal Utility District (EBMUD) will begin the work of repairing its sewer along segments of Buena Vista Avenue. Construction will extend to February 2023.

"This major project is being undertaken as an emergency to address possible pipeline failure and the potential for sinkholes," the City of Alameda said in a statement.

During the project, parts of Buena Vista Avenue will be closed in the west bound direction 24 hours a day, 7 days a week, according to the city. Trucks will be diverted from Buena Vista Avenue to Lincoln Avenue between Grand Street and Constitution Way, and street parking will be restricted. EBMUD will work to control odor; however, there may be intermittent impacts.

Find out what's happening in Alamedafor free with the latest updates from Patch.

The work will require excavation at three locations in Buena Vista Avenue, impacting between 8th Street and Ohlone Street. The work is scheduled to start in October 2022 and extend to February 2023. Work hours are scheduled for 7 am to 7 pm and include some work on Saturdays.

More information about the project is available at https://www.ebmud.com/about-us...