Ground Breaking Next Week At Pleasant Hill Community Center

Board members have awarded the project to DL Falk Construction Co. for $8.2 million.

The $8.2 million Recreation and Park District's Community Center is scheduled to begin construction next week, after the official groundbreaking event on Wednesday, Aug. 8 at 320 Civic Drive.

The Recreation and Park District Board members decided in May to rebid the project after the lowest bid came in $1.6 million over the budget. DL Falk Construction Co. submitted a bid for $8.2 million and was awarded the contract, according to a district release.

The board has agreed to cut some of the amenities out of the original design, according to the Contra Costa Times, including an entry canopy and high-end building materials. 

Find out what's happening in Pleasant Hillfor free with the latest updates from Patch.

Construction is expected to begin this month, with the goal of opening the Community Center in the winter of 2013. 