Auditor Timothy O'Brien's believes the City of Denver risks overpaying for projects like the Great Hall because of the lack of project management and oversight of construction work.
Auditor Timothy O'Brien's believes the City of Denver risks overpaying for projects like the Great Hall because of the lack of project management and oversight of construction work. (CBS)

By CBS Denver Staff:

Denver's auditor believes Denver International Airport's Great Hall Project needs more oversight. Denver Auditor Timothy O'Brien released a report that states the project is at risk of overspending, a lack of transparency and unfair contracting.

O'Brien believes the City of Denver risks overpaying for projects like the Great Hall because of the lack of project management and oversight of construction work.

Find out what's happening in Denverfor free with the latest updates from Patch.

Read more at CBS Denver


CBS Local Digital Media personalizes the global reach of CBS-owned and operated television and radio stations with a local perspective.

Find out what's happening in Denverfor free with the latest updates from Patch.